top of page

selected work

Engineering in Practice.

A selection of projects highlighting practical engineering solutions, technical problem-solving, and verified system performance.

Anonymized Issues Log and Plan AHU

01 | QAQCx

Identifying Problems Before Construction.

During a technical review of an outdoor air-handling unit, FUNCTION identified a bypass damper located in the regeneration air stream rather than the outside-air stream. The equipment submittal had already been approved, and the unit was approaching fabrication.

THE CHALLENGE

Through independent equipment submittal review and coordination with the project team, FUNCTION identified the configuration error and documented the required correction. Additional reviews addressed equipment compatibility, control requirements, and construction coordination.

FUNCTION'S ROLE

Among other resolved issues, the manufacturer corrected the bypass damper arrangement before fabrication, avoiding a potentially costly field modification and helping preserve the intended system operation.

THE OUTCOME

02 | MECHANICAL ENGINEERING

Phased HVAC Modernization Without a Complete Building Shutdown.

THE CHALLENGE

Upgrading aging HVAC systems in an occupied commercial building requires balancing equipment performance, construction constraints, available infrastructure, and owner budgets. A complete system replacement is not always practical or necessary.

FUNCTION'S ROLE

FUNCTION develops mechanical engineering solutions that integrate new equipment with existing building systems. Designs consider phased construction, hydronic distribution, equipment selection, building automation integration, and opportunities for future system improvements.

THE OUTCOME

A practical modernization strategy that allows improvements to proceed in manageable phases while preserving usable infrastructure, supporting continued building operation, and providing flexibility for future upgrades.

Anonymized CHW Riser Phased
Anonymized Flushing Issue Data Center

03 | COMMISSIONING & TROUBLESHOOTING

Finding the Root Cause of Hydronic Problems.

THE CHALLENGE

A multi-phase data center project experienced recurring chilled-water flow problems, including suspended solids, air accumulation and system performance deficiencies. Repeated corrective efforts addressed symptoms without fully resolving the underlying issue.

FUNCTION'S ROLE

FUNCTION investigated the system through construction documentation, flushing procedures, field observations, and operational analysis. The review identified a flushing configuration that incorrectly isolated significant portions of the piping system, preventing the intended flow through those sections.

THE OUTCOME

The investigation identified a fundamental problem in the flushing procedure and its field implementation, providing the project team with a technically supported explanation of the recurring deficiencies and a basis for corrective action.

Have a Technical Challenge?

Whether you're planning a mechanical system upgrade, evaluating construction risks, or troubleshooting a complex system, FUNCTION brings practical engineering experience to the conversation.